Posted on January 18, 2013

Qatari liquefied natural gas producer RasGas plans three maintenance shutdowns in 2013, Bloomberg informs. The company’s fourth train will halt in April, while train 3 will be shut in September and unit 7 will undergo repairs in November. The repairs will last about three to four weeks.

RasGas oversees and manages all the operations associated with seven LNG trains and it has a total production capacity of approximately 37 million tonnes per annum.


source: LNG World News

Advertisement
Qatar Airways 5 Star Travel

Categories: